Project: Greg's_RV-10   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Greg Kochersperger   -  
Project:   Vans - RV-10
Total Hours:1327.9
Total Flight Time:1.1
Start/Last Date:Jan 15, 2021 - No Finish Date
Engine:IO-540
Propeller:TBD
Panel:Garmin G3X
 
Friendly URL: https://eaabuilderslog.org?s=Greg's_RV-10

Home or Last Project Picture

Oct 28, 2023     Replace fwd fuse rib - (1.0 hour) Category: 31: Upper Fuse
Had just the one LCP that I'm replacing, the center rib in the forward fuse.

Just a little time to take things apart and reassemble. Revisiting this section though I did realize that I don't have the F-1083Q throttle cable support for the quadrant option. I'll need to order one, but with the issues at Van's, who knows when I'll get it.
 